Gerald Moore, Gilbane Building Company. We’re at block 58, the new Heinz 48-story
tower. The efforts for this project began back in
July 2018. In the last month, been many hours preparation
with the city of Houston to close multiple streets for this weekend’s event. After 28 days of installing three million
pounds of rebar, we’re set on the cusp of a fourteen thousand yard pour with six pumps
and probably 100-120 guys from Baker are going to be down in the hole. Gilbane supporting them with staffs up on
top. So as this concrete pour will finish this
Sunday morning, then the sea of workers will come back in to demobilize, remove, pickup
all of the 20 blocks of lane closures for this event. And be wrapping down, cleaning the streets,
restoring all of the streets open back to the local businesses.